Supreme Court on unfinished work vs. defects
Attorney Choi Seung-jun of Seongji Partners explains how Korea's Supreme Court distinguishes unfinished construction from defects in completed work, a distinction that can change both the final construction payment and the burden of liquidated damages for delay.
Korea's Supreme Court has held that construction counts as complete by social norms once the final scheduled process is finished and the main structural parts are built as agreed, even if some repairs remain; those remaining items are defects, not unfinished work. In a dispute over exhibits at the Taejon Expo, the court ruled that the owner could not claim delay damages on the premise that the work had not been completed by the agreed date.
Should a project be considered unfinished if not every issue flagged in the completion inspection has been fixed? This is one of the most common points of contention between project owners and contractors. How incomplete work is distinguished from defects in completed work can change not only the final construction payment but also who bears liquidated damages for delay.
In such disputes, owners often argue that the work is incomplete because of poor finishing or malfunctioning equipment, while contractors counter that they have finished the contractual processes and that any remaining work is merely defect repair.
The legal standard is not whether the construction was performed perfectly, but whether the work defined in the contract was completed according to social norms. The mere existence of defects does not establish that the construction is incomplete.
In a ruling handed down on Oct. 10, 1997 (Case No. 97Da23150), the Supreme Court set out the criteria for distinguishing incomplete construction from defects.
Construction is incomplete if it stopped midway and the final process originally scheduled was not finished. Conversely, if the final process has been completed and the main structural parts have been built as agreed, so that the work is complete by social norms, any parts that still need repair should be treated as defects in a completed object.
Whether the final process has been completed cannot be decided solely by the contractor's submission of a completion report or by the result of the owner's completion inspection. The Supreme Court's position is that this must be judged objectively, based on the specific terms of the contract and the principle of good faith.
The ruling arose from a dispute over the production, installation and staging of exhibits for the Exhibition Energy Hall at the Taejon Expo exhibition grounds.
The contractor finished the work by the agreed completion date and submitted a completion report, but the owner notified it that certain exhibition areas had failed the completion inspection. The issues cited included securing heat exchangers and floor installations, training operating staff, equipment breakdowns and finishing touch-ups.
The facilities later passed inspection after remedial work, but the owner argued that liquidated damages for the period beyond the agreed completion date should be deducted from the construction payment.
The court focused on the actual nature of the work rather than the labels attached to the inspection findings. The heat-exchange work was a request to improve a system that had already been installed, and the floor issue involved securing parts that had already been installed. The remaining items concerned document submission, training and rework due to breakdowns.
The fact that the owner actually took over the facilities it had failed in the inspection and used them during the Expo also served as a basis for the decision.
The Supreme Court upheld the lower court's finding that the work was not incomplete but was a case of defects arising in a completed object. Claims for defect repair or for damages caused by defects are a separate matter, the court said, but damages cannot be claimed on the premise that the construction was not completed by the agreed date.
The ruling separates liability for delayed completion from liability for defects in completed construction.
However, the "main structural parts" mentioned in the precedent should not be read only as a building's physical frame, such as columns, beams or walls. The case itself involved the production, installation and staging of exhibits rather than ordinary building construction.
For equipment installation, the question is whether the functions specified in the contract were achieved; if the work included operation and staging, whether those tasks were finished. This is why completion is difficult to judge by progress rates or outward appearance alone.
The end point for calculating liquidated damages is also tied to this distinction. Under an ordinary construction contract, the entire repair period cannot be counted as delay simply because defect repairs were carried out after the work was complete by social norms.
The outcome may differ if the parties have agreed otherwise. In a ruling handed down on Jan. 14, 2010 (Case Nos. 2009Da7212 and 7229), the Supreme Court addressed the validity of special agreements on completion inspections and liquidated damages.
The ruling indicates that if there are special circumstances aimed at securing full performance of the contract — such as making the owner's completion inspection a condition for payment, or agreeing that the contractor bears liquidated damages until it passes a re-inspection after defect repair — that agreement must be followed.
However, the Supreme Court did not recognize a special agreement merely because the contract contained a clause defining the date of passing the completion inspection as the completion date.
That clause could be read as setting out the division of completion-related tasks and the principles for sharing costs before and after construction. The Supreme Court overturned the lower court's decision, which had fixed the end point for calculating liquidated damages based on the wording that made the inspection pass date the completion date.
The decision underscores that not only specific wording but the overall structure of the contract and the purpose of the relevant clauses must be reviewed comprehensively.
In actual construction disputes, records that show the state of the site at the time of completion are crucial.
Owners need to verify specifically which processes were not carried out, based on contract drawings, specifications and progress schedules. This means distinguishing whether the work is a touch-up of parts already built or whether processes scheduled in the contract themselves remain unfinished.
Contractors, too, will find it hard to prove completion merely by submitting a completion report. Work records for each process, photos and videos from the time of completion, test-run results for major equipment, inspection records and site meeting minutes can serve as objective evidence.
Whether the owner took over and used the facilities is also a factor, but use alone does not establish that construction was complete. The actual scope of use, the state of the work at the time and the work specified in the contract must be examined together.
At the contract stage, the relationship among the completion date, the completion inspection procedure and the end point for calculating liquidated damages should be clearly defined. Even when the parties agree the work is complete but some defect repairs remain, documenting the confirmation of completion, the items to be repaired, the work schedule and the verification method separately is a way to prevent disputes.
Choi Seung-jun, Managing Attorney, Seongji Partners LLC